What’s the Timeline from Consultation to Activation?

Home / FAQ / What’s the Timeline from Consultation to Activation?

What’s the Timeline from Consultation to Activation?

At Sunmate, we aim to make your solar journey smooth and straightforward. From your first consultation to your system going live, here’s what you can expect:

📅 Typical Timeline: About 1 Month and Up

  1. Consultation & Site Survey (1 week):
    We discuss your needs, assess your roof, and design your custom system.
  2. Design & Quotation (1 week):
    We prepare your tailored quote, including panel options and FoxESS components.
  3. Permitting & Approvals (1–2 weeks):
    We handle all the paperwork, including G99/DNO applications and MCS certification.
  4. Installation Scheduling (depends on availability):
    We book your installation date—usually within 1–2 weeks after approvals.
  5. Installation Day(s) (1–3 days):
    Our expert team installs your system, including FoxESS equipment and any optional extras like batteries or changeover switches.
  6. Commissioning & Activation (Same day):
    We test everything, activate your system, and show you how to use FoxESS’s Fox Cloud 2.0 monitoring.

🔑 Summary

From start to finish, expect roughly 4 to 6 weeks depending on approvals and scheduling. We’ll keep you updated at every step!

Want us to check your earliest possible installation date?

Ready to Start Saving on Energy Bills?

We’re happy to answer your questions or provide a free consultation. Just send us a message!